Mechanic's lien deadlines in California
California mechanic's lien deadlines at a glance
Contractor hired by the owner
By the earlier of 90 days after the work is completed or 60 days after the owner records a notice of completion or cessation
Subcontractors and suppliers
By the earlier of 90 days after completion or 30 days after a notice of completion or cessation
Rule from
Cal. Civ. Code 8412 and 8414 (Counsel Stack)
The rule in California
Under California Civil Code 8412, a direct contractor (one with a contract with the owner) may not enforce a mechanics lien unless it records a claim of lien after it completes its direct contract and before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion or cessation. Under 8414, any other claimant, such as a subcontractor or supplier, must record its claim of lien after it stops providing work and before the earlier of 90 days after completion of the work of improvement or 30 days after the owner records a notice of completion or cessation.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for California
- Small claims court in California
- Homestead exemption in California
- What a home seller must disclose in California
- How long a court judgment lasts in California
- Interest on a court judgment in California
- LLC fees in California
- Deadlines to sue in California
- Bounced check fees in California
Owed money for work or materials?
See your next stepsSources
- Cal. Civ. Code 8412: direct contractor, time to record a claim of lien (Counsel Stack)
- Cal. Civ. Code 8414: other claimants, time to record a claim of lien (Counsel Stack)
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in California from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in California.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/california/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/california/">Mechanic's lien deadlines in California</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.