Mechanic's lien deadlines in Florida
Florida mechanic's lien deadlines at a glance
Contractor hired by the owner
Within 90 days after the lienor last furnished labor, services or materials
Subcontractors and suppliers
The same 90 days after the last labor, services or materials
Rule from
Fla. Stat. 713.08(5) (2026)
The rule in Florida
Under Florida Statutes 713.08(5), a claim of lien may be recorded at any time while the work is in progress or afterward, but not later than 90 days after the lienor last furnished labor, services or materials. If the original contract is terminated under 713.07(4), a lien that attached before the termination must be recorded within 90 days after the termination or 90 days after the lienor's final furnishing, whichever comes first. The same deadline applies to contractors, subcontractors and suppliers; the notice to owner that lienors without a direct contract must serve under 713.06 was not read.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Florida
- Small claims court in Florida
- Homestead exemption in Florida
- What a home seller must disclose in Florida
- How long a court judgment lasts in Florida
- Interest on a court judgment in Florida
- LLC fees in Florida
- Deadlines to sue in Florida
- Bounced check fees in Florida
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Florida from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Florida.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/florida/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/florida/">Mechanic's lien deadlines in Florida</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.