Mechanic's lien deadlines in Georgia
Georgia mechanic's lien deadlines at a glance
Contractor hired by the owner
Within 90 days after completing the work or furnishing the materials
Subcontractors and suppliers
The same 90 days
Rule from
O.C.G.A. 44-14-361.1 (Justia, 2021 Georgia Code)
The rule in Georgia
Under O.C.G.A. 44-14-361.1(a)(2) (2021 Georgia Code on Justia), a person claiming a lien must file the claim of lien for record in the office of the clerk of superior court of the county where the property is located within 90 days after completing the work, furnishing the architectural or engineering services, or furnishing the materials or machinery, and must send a copy to the owner by registered or certified mail or statutory overnight delivery no later than two business days after filing. Under (a)(3), the claimant must start a lien action within 365 days after filing the claim and, within 30 days after starting it, file a sworn notice of the action with the clerk. Later amendments to the section were not checked.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Georgia
- Small claims court in Georgia
- Homestead exemption in Georgia
- What a home seller must disclose in Georgia
- How long a court judgment lasts in Georgia
- Interest on a court judgment in Georgia
- LLC fees in Georgia
- Deadlines to sue in Georgia
- Bounced check fees in Georgia
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Georgia from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Georgia.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/georgia/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/georgia/">Mechanic's lien deadlines in Georgia</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.