Mechanic's lien deadlines in Hawaii
Hawaii mechanic's lien deadlines at a glance
Contractor hired by the owner
File an application and notice with the circuit court within 45 days after the improvement is completed
Subcontractors and suppliers
The same 45 days
Rule from
HRS 507-43 (Hawaii Legislature)
The rule in Hawaii
Under Hawaii Revised Statutes 507-43 (official text, last amended L 2019, c 111), any person claiming a mechanic's and materialman's lien must apply to the circuit court of the circuit where the property is located, and the Application and Notice must be filed not later than 45 days after the date of completion of the improvement. A copy must be served in the manner prescribed for service of summons, and it is returnable not less than 3 nor more than 10 days after service. How the date of completion is set is in other sections that were not read.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Hawaii
- Small claims court in Hawaii
- Homestead exemption in Hawaii
- What a home seller must disclose in Hawaii
- How long a court judgment lasts in Hawaii
- Interest on a court judgment in Hawaii
- LLC fees in Hawaii
- Deadlines to sue in Hawaii
- Bounced check fees in Hawaii
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Hawaii from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Hawaii.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/hawaii/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/hawaii/">Mechanic's lien deadlines in Hawaii</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.