Mechanic's lien deadlines in Illinois
Illinois mechanic's lien deadlines at a glance
Contractor hired by the owner
Within 4 months after completion to keep the lien against third parties; 2 years against the owner
Subcontractors and suppliers
Written notice to the owner within 90 days after completing the work
Rule from
770 ILCS 60/7 and 60/24 (Illinois General Assembly)
The rule in Illinois
Under 770 ILCS 60/7(a) (source P.A. 96-654), a contractor must, within 4 months after completion (or after completing extra work), either bring an action to enforce the lien or file a verified claim for lien with the county recorder to keep the lien against creditors, encumbrancers and purchasers; as to the owner, the claim may be filed within 2 years after completion of the contract. Under 60/24(a), a subcontractor or supplier must serve written notice of its claim and the amount due within 90 days after completing its work, by registered or certified mail with return receipt (delivery to the addressee only) or by personal service on the owner of record or the owner's agent, architect or superintendent, and on the lender if known.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Illinois
- Small claims court in Illinois
- Homestead exemption in Illinois
- What a home seller must disclose in Illinois
- How long a court judgment lasts in Illinois
- Interest on a court judgment in Illinois
- LLC fees in Illinois
- Deadlines to sue in Illinois
- Bounced check fees in Illinois
Owed money for work or materials?
See your next stepsSources
- 770 ILCS 60/7: time to file a claim for lien (Illinois General Assembly)
- 770 ILCS 60/24: subcontractor notice to the owner (Illinois General Assembly)
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Illinois from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Illinois.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/illinois/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/illinois/">Mechanic's lien deadlines in Illinois</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.