Mechanic's lien deadlines in Maryland

Maryland mechanic's lien deadlines at a glance

Contractor hired by the owner

Petition the circuit court within 180 days after the work was finished or the materials furnished

Subcontractors and suppliers

The same 180 days (subcontractors must also give notice to the owner under 9-104, not read)

Rule from

Md. Real Prop. 9-105(a) (Maryland General Assembly, 2026)

The rule in Maryland

Under Maryland Real Property 9-105(a) (2026 text on the General Assembly site), a person claiming a mechanic's lien must file a petition to establish it in the circuit court for the county where the land, or any part of it, is located within 180 days after the work was finished or the materials furnished. The notice that a subcontractor must give the owner under 9-104 was not read.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Maryland

Owed money for work or materials?

See your next steps

Sources

  1. Md. Real Prop. 9-105: petition to establish lien (Maryland General Assembly, 2026, PDF)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Maryland from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Maryland.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/maryland/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/maryland/">Mechanic's lien deadlines in Maryland</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.