Michigan mechanic's lien deadlines at a glance

Contractor hired by the owner

Within 90 days after the claimant last furnished labor or material

Subcontractors and suppliers

The same 90 days

Rule from

MCL 570.1111 (Michigan Legislature PDF)

The rule in Michigan

Under Michigan Compiled Laws 570.1111(1) of the Construction Lien Act (1980 PA 497, amended 1982), a construction lien ceases to exist unless a claim of lien is recorded with the register of deeds of each county where the property is located within 90 days after the lien claimant's last furnishing of labor or material. Under subsection (5), a copy of the recorded claim must be served on the owner's designee (or the owner or lessee if no designee is named) within 15 days after recording. Notices of furnishing required before a claim are in other sections, not read.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Michigan

Owed money for work or materials?

See your next steps

Sources

  1. MCL 570.1111: recording a claim of lien (Michigan Legislature, PDF)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Michigan from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Michigan.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/michigan/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/michigan/">Mechanic's lien deadlines in Michigan</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.