Mechanic's lien deadlines in Mississippi

Mississippi mechanic's lien deadlines at a glance

Contractor hired by the owner

File with the chancery clerk within 90 days after the claimant last provided work, labor, services or materials

Subcontractors and suppliers

The same 90 days

Rule from

Miss. Code 85-7-405(1)(b) (Justia, 2015 Mississippi Code)

The rule in Mississippi

Under Mississippi Code 85-7-405(1)(b) (2015 text on Justia), a construction lien claim must be filed in the office of the clerk of the chancery court of the county where the property is located within 90 days after the claimant's last work performed or labor, services or materials provided, and the lien must include a notice to the owner that the owner has the right to contest it; without that notice the lien is invalid. Later amendments to the section were not checked.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Mississippi

Owed money for work or materials?

See your next steps

Sources

  1. Miss. Code 85-7-405: lien claim, filing (Justia, 2015 Mississippi Code)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Mississippi from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Mississippi.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/mississippi/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/mississippi/">Mechanic's lien deadlines in Mississippi</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.