Mechanic's lien deadlines in Montana
Montana mechanic's lien deadlines at a glance
Contractor hired by the owner
File with the county clerk and recorder within 90 days after the final services or materials, or after the owner files a notice of completion
Subcontractors and suppliers
The same 90 days
Rule from
MCA 71-3-535 (Counsel Stack, 2026)
The rule in Montana
Under Montana Code 71-3-535 (Counsel Stack text, cited as 2026, last amended 1999), a construction lien does not attach and cannot be enforced unless the person files it with the county clerk and recorder of the county where the improved real estate is located not later than 90 days after the person's final furnishing of services or materials, or after the owner files a notice of completion under 71-3-533. Notice rules in other sections of the Construction Lien Act were not read.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Montana
- Small claims court in Montana
- Homestead exemption in Montana
- What a home seller must disclose in Montana
- How long a court judgment lasts in Montana
- Interest on a court judgment in Montana
- LLC fees in Montana
- Deadlines to sue in Montana
- Bounced check fees in Montana
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Montana from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Montana.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/montana/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/montana/">Mechanic's lien deadlines in Montana</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.