Mechanic's lien deadlines in Oklahoma

Oklahoma mechanic's lien deadlines at a glance

Contractor hired by the owner

Within 4 months after the materials or equipment were last furnished or the labor last performed

Subcontractors and suppliers

Within 90 days after the last materials, equipment or labor under the subcontract

Rule from

42 O.S. 142 (Justia 2025) and 143 (Justia 2018)

The rule in Oklahoma

Under 42 O.S. 142 (2025 text on Justia), a person claiming a lien must file a statement verified by affidavit in the office of the county clerk of the county where the land is located within four months after the date the material or equipment was last furnished or the labor last performed (for trees, vines, plants or hedges, after the planting). Under 143 (2018 text on Justia, last amended by Laws 2013, c. 78), a person who furnished materials, equipment or labor under a subcontract must file the verified statement with the county clerk within 90 days after the date the material or equipment was last furnished or the labor last performed, and the owner cannot be sued by that claimant until the 90 days have run. Pre-lien notices for residential property in 142.6 were not read.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Oklahoma

Owed money for work or materials?

See your next steps

Sources

  1. 42 O.S. 142: lien statement, time to file (Justia, 2025 Oklahoma Statutes)
  2. 42 O.S. 143: subcontractor lien statement (Justia, 2018 Oklahoma Statutes)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Oklahoma from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Oklahoma.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/oklahoma/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/oklahoma/">Mechanic's lien deadlines in Oklahoma</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.