Mechanic's lien deadlines in Oregon
Oregon mechanic's lien deadlines at a glance
Contractor hired by the owner
Within 75 days after the claimant stopped work or 75 days after construction is completed, whichever is earlier
Subcontractors and suppliers
The same 75-day rule
Rule from
ORS 87.035(1) (oregon.public.law, 2023 edition)
The rule in Oregon
Under Oregon Revised Statutes 87.035(1) (2023 edition, text unchanged since 1987), a person claiming a lien for labor, rented equipment or materials under 87.010(1) or (2) must perfect it by filing a claim of lien not later than 75 days after it stopped providing the labor, equipment or materials, or 75 days after construction was completed, whichever is earlier; other lien claimants have until 75 days after completion of construction. Notices that suppliers and contractors must give before the lien under other sections were not read.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Oregon
- Small claims court in Oregon
- Homestead exemption in Oregon
- What a home seller must disclose in Oregon
- How long a court judgment lasts in Oregon
- Interest on a court judgment in Oregon
- LLC fees in Oregon
- Deadlines to sue in Oregon
- Bounced check fees in Oregon
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Oregon from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Oregon.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/oregon/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/oregon/">Mechanic's lien deadlines in Oregon</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.