Mechanic's lien deadlines in Pennsylvania

Pennsylvania mechanic's lien deadlines at a glance

Contractor hired by the owner

Within 6 months after the claimant completes its work

Subcontractors and suppliers

The same 6 months

Rule from

49 P.S. 1502 (FindLaw, current as of 1 January 2026)

The rule in Pennsylvania

Under 49 P.S. 1502 of the Pennsylvania Mechanics' Lien Law, every claimant must file a claim with the prothonotary within six months after completing its work, and must serve written notice of the filing on the owner within one month after filing (by an adult, as for a writ of summons in assumpsit, or by posting on a conspicuous public part of the improvement if that fails), then file an affidavit or acceptance of service within 20 days after service. Failure to comply can be grounds for striking the claim. Notices that subcontractors must give before filing are in other sections, not read.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Pennsylvania

Owed money for work or materials?

See your next steps

Sources

  1. 49 P.S. 1502: filing and service of the claim (FindLaw, current as of 1 January 2026)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Pennsylvania from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Pennsylvania.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/pennsylvania/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/pennsylvania/">Mechanic's lien deadlines in Pennsylvania</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.