Mechanic's lien deadlines in Vermont

Vermont mechanic's lien deadlines at a glance

Contractor hired by the owner

File a notice of lien with the town clerk within 180 days after payment for the last labor or materials became due

Subcontractors and suppliers

The same 180 days, after first giving the owner written notice of the claim

Rule from

9 V.S.A. 1921 (Counsel Stack)

The rule in Vermont

Under 9 V.S.A. 1921 (Counsel Stack text, last amended 2003, No. 144), a person who works under a contract with the owner has a lien on the improvements and the lot of land. A subcontractor or supplier working under a contract with the owner's agent, a contractor or a subcontractor gets a lien only by giving the owner or the owner's agent written notice that it will claim a lien, and the lien then covers the part of the contract price still unpaid when the notice is received. Under subsection (c), the lien does not last more than 180 days from the date payment became due for the last labor or materials unless a notice of the lien is filed in the office of the town clerk. The deadline to sue on the lien is in other sections that were not read.

What this covers

A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.

Practical steps

  1. Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
  2. Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
  3. Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
  4. If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.

Do you need a lawyer?

Often without a lawyer

  • Finding the deadline and the filing office
  • Asking the recorder or clerk for the lien form and the fee

Talk to a lawyer

  • The deadline is close or may have passed
  • A lien was recorded against your home
  • The project is large or has several contractors

Related guides for Vermont

Owed money for work or materials?

See your next steps

Sources

  1. 9 V.S.A. 1921: extent of lien, notice (Counsel Stack)

Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Vermont from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.

Cite this page

“Mechanic's lien deadlines in Vermont.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/vermont/

Link code: <a href="https://locallawyersonline.com/mechanics-lien/vermont/">Mechanic's lien deadlines in Vermont</a> (Local Lawyers Online)

You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.