Mechanic's lien deadlines in Wyoming
Wyoming mechanic's lien deadlines at a glance
Contractor hired by the owner
File the lien statement within 150 days after the last work or materials, or substantial completion if earlier
Subcontractors and suppliers
Within 120 days after the last work or materials, or substantial completion if earlier
Rule from
Wyo. Stat. 29-2-106 (Counsel Stack, 2026)
The rule in Wyoming
Under Wyoming Statutes 29-2-106(a) (Counsel Stack text, cited as 2026), a contractor asserting a lien must file its lien statement within 150 days, and every other lien claimant, including subcontractors and materialmen, within 120 days, counted from the earlier of the last day work was performed or materials were furnished under the contract, or the date of substantial completion of the project; for a subcontractor the period can also run from the last day it worked at the contractor's direction. An owner may record a notice of substantial completion, and the parties may agree in a signed, notarized and recorded agreement to extend the filing time up to twice the normal period. A contract between the owner and the contractor cannot limit a subcontractor's or supplier's right to file. Notice rules in other sections were not read.
What this covers
A mechanic's lien (also called a construction lien) is a claim against land and buildings that a contractor, subcontractor, worker or supplier who was not paid for work or materials on that property can record. If the lien is not recorded or filed in time, the right to it is usually lost. This page gives the deadline to record or file the lien under the state law named above. Many states also require a notice to the owner before or during the work, a copy of the lien sent to the owner, and a lawsuit to enforce the lien within a further deadline. The rule above mentions those steps only where the section read does, so check them too.
Practical steps
- Write down the last day you worked on the property or delivered materials. Most deadlines count from that day or from the completion of the project.
- Check whether the state requires a notice to the owner before the lien, and whether the owner recorded a notice of completion, which can shorten the time.
- Record or file the lien with the office named in the rule (often the county recorder or a court clerk) and keep a copy with the filing date.
- If you own the property and a lien was recorded against it, read it, note the date, and talk to a lawyer before you pay it or sell the property.
Do you need a lawyer?
Often without a lawyer
- Finding the deadline and the filing office
- Asking the recorder or clerk for the lien form and the fee
Talk to a lawyer
- The deadline is close or may have passed
- A lien was recorded against your home
- The project is large or has several contractors
Related guides for Wyoming
- Small claims court in Wyoming
- Homestead exemption in Wyoming
- What a home seller must disclose in Wyoming
- How long a court judgment lasts in Wyoming
- Interest on a court judgment in Wyoming
- LLC fees in Wyoming
- Deadlines to sue in Wyoming
- Bounced check fees in Wyoming
Owed money for work or materials?
See your next stepsSources
Last checked: November 16, 2026. This page covers the deadline to record or file a mechanic's (construction) lien in Wyoming from the state law named above. Notice rules before the lien, the deadline to sue on the lien, and rules for public projects can differ, so confirm the steps with the recorder, the court clerk or a lawyer. It is general information, not legal advice.
Cite this page
“Mechanic's lien deadlines in Wyoming.” Local Lawyers Online, last checked November 16, 2026. https://locallawyersonline.com/mechanics-lien/wyoming/
Link code: <a href="https://locallawyersonline.com/mechanics-lien/wyoming/">Mechanic's lien deadlines in Wyoming</a> (Local Lawyers Online)
You may quote the facts on this page. Please credit Local Lawyers Online, and check the official sources listed on this page before you rely on a figure.